Subsea Pipeline Tie-In
Wednesday, February 17, 2016Subsea tie-in is typically made by diver-assisted flange connectors for shallow water pipelines and diverless remotely operated vehicle (ROV) connectors for deepwater pipelines.
There are three types of
connectors available: flange, clamp (Graylok type), and collet connectors.
Clamp or collet connector is more favorable over the flange connector due to
ROV operability, offshore connection time, and available tie-in tools from
contractors.
The methods of pipeline tie-in
are explained below:
Spoolpiece
Divers measure and then assist
the installation of a piece of pipe to fit in between the two ends of flowline
to be tied together. Misalignment of the two pipes can be accommodated by
installing bends into the spool, and inaccuracies in placing the pipelines down
can be accommodated when the spool is made up (after diver measurements).
The connection method can either
be by flanges or welding. The welding method requires a hyperbaric habitat.
From a design viewpoint, should there be large flowline expansion, then this
can also be accommodated by incorporating a dogleg in the spool. This will
permit expansion of the pipe without transmitting high loads into the adjacent
pipe.
Lateral Pull
Lateral deflection involves
positioning the flowline end to one side of the target structure and then
pulling it laterally into position. The
flowline may be pulled towards the target by a single wire, or a series of
wires may be developed through dead-man anchors to give greater control of
alignment. A bell mouth or stab-in guides usually assist final alignment.
For large diameters such as
export lines or bundles, it is necessary to make a length of pipeline neutrally
buoyant. This gives greater flexibility and reduces the pull forces, but can
expose the pipe to large current forces.
J-tube Pull-in
This method requires the flowline
to have the capacity to easily move axially over a relatively large distance.
This limits the option to pulling the flowline directly from the pipelay
vessel. The method of J-tube pull-in is to connect the flowline to a wire and,
by pulling the wire, to pull the flowline through a riser (J-tube) up to the
topsides of the platform. This method requires the J-tube to be of a reasonably
large diameter compared to the flowline.
Connect and Lay Away
This method is very similar to
the J-tube pull-in method with the exception that the tie-in is performed
subsea. This method is usually applied in diverless operations, where a
mechanical connecting system will be utilized to perform the connection. This
system is mainly used at subsea manifolds/wellheads, where the water depth
prohibits the use of divers. This is the only system developed for performing
diverless connection of pipelines.
Stalk-on
The stalk-on method is primarily
used in shallow water applications (less than 40 m) and hence would only be
applicable in the Southern North Sea. The method involves laying the flowline
down adjacent to the jacket it shall be tied into. The vessel maneuvers over
the flowline, lifts it up and welds on (or flanges on) the jacket riser. The
pipeline and riser are then lowered onto the seabed/jacket. The jacket clamps
are subsequently closed around the riser.
--
Source:
Lee, Jaeyoung. Introduction to Offshore Pipelines and Risers. 2007.
Bai, Yong and Bai, Qiang. Subsea Pipelines And Risers. USA: Elsevier Inc. 2005.
0 komentar