Offshore Pipeline Installation
Monday, February 01, 2016S-Lay (Shallow to Deep)
The most common method of
pipeline installation in shallow water is the S-lay method. In the S-lay
method, the welded pipeline is supported on the rollers of the vessel and the stinger,
forming the over-bend. Then it is suspended in the water all the way to the seabed,
forming the sag-bend. The over-bend and sag-bend form the shape of an ‘‘S.’’
In the S-lay method, tensioners
on the vessel/barge pull on the pipeline, keeping the whole section to the
seabed in tension. The reaction of this pull is taken up by anchors installed
ahead of the barge or, in the case of a dynamically positioned (DP) vessel, by thrusters.
These barges/vessels are fitted with tension machines, abandonment and recovery
(A&R) winches, and pipe handling cranes. The firing line for welding the
pipe may be placed in the center of the barge or to one side. The firing line
consists of a number of stations for welding, NDE, and field joint application.
The field joint station is located after the NDE station and the tension
machines.
J-Lay (Intermediate to Deep)
To keep up with the discovery of
deepwater oil and gas fields, the J-lay system for pipeline installation was
invented. In this system, lengths of pipe are welded in a near vertical or vertical
position and lowered to the seabed. In
this configuration, the pipeline from the surface to the seabed is one large
radius bend resulting in lower stresses than an S-lay system in the same water
depth. There is no over-bend, and a large stinger required in S-lay to support
the pipe in deepwater is eliminated. The horizontal forces required to maintain
this configuration are much smaller than required for an S-lay system. This
lends itself for DP shipshape vessels and derrick barges to be equipped with a
J-lay tower. Large J-lay towers have been installed on the world’s largest
heavy lift vessels—Saipem’s S7000 and Heerema’s Balder—as well as smaller towers
on other vessels such as Stolt’s Polaris, McDermott’s DB 50, and Technip’s Deep
Blue. Normally, the J-lay process is slower than S-lay, but since the large
J-lay towers are capable of handling prefabricated quad joints (160 feet long),
the speed of pipelaying is increased.
The J-lay method is normally used
in water depths greater than 500 feet. These water depths are normally too
great for moored lay vessels to operate, because the required tensions and pipe
bending stresses are too large.
Reel lay (Intermediate to Deep)
Reel pipelay is a method of
installing pipelines in the ocean from a giant reel mounted on an offshore
vessel. Pipelines are assembled at an onshore spool-base facility and spooled onto
a reel which is mounted on the deck of a pipelay barge. The first application
of the reeled pipeline was on D-Day when the allies were supplied with fuel
across the English Channel using a small diameter pipeline unreeled from a
vessel. Commercial application of reeled pipeline technology was not available
until the early 1970s when Santa Fe Corporation built the first reel vessel.
Reel technology also provides a
safer and more stable work environment, thus speeding pipeline installation.
Reeled pipelines can be installed up to 10 times faster than conventional pipelay.
The greater speed allows pipelines to be laid during a short weather window. This
can extend the normal construction season. Reel pipelay can be used on
pipelines up to 18 inches in diameter.
The reel method reduces labor
costs by permitting much of the welding, x-raying, corrosion coating, and
testing to be accomplished onshore, where labor costs are generally lower than
comparable labor costs offshore. After the pipeline is reeled onto the drum of the
pipelaying vessel, it is taken to the offshore location for installation. The
reeled pipeline can be installed in an S-lay method or J-lay method depending
on the design of the reel vessel and the depth of water. Reel vessels can have
vertical reels or horizontal reels.
Horizontal reel vessels lay
pipelines in shallow to intermediate water depths using a stinger and S-lay
method. The station-keeping of vessels with horizontal reels can be by anchors
or DP.
The vertical reel vessel can
normally install pipelines from the intermediate water depths to deepwater and
station-keeping is always DP. For deepwater, the J-lay configuration is used
and no stinger is required.
The pipe is unreeled,
straightened, de-ovalized, and connected to the wire rope from the seabed
pre-installed hold back anchor. The sagbend stresses are controlled by the
tensioning system on the reel vessel. The vessel moves ahead while it slowly
unreels the pipeline from the drum. When the end of the pipeline on the drum is
unreeled, a pullhead connected to a wire rope is attached. The end of the pipeline
is lowered to the seabed by paying out the A&R wire rope from the reel
vessel slowly in a controlled method always maintaining sufficient tension in
the pipeline. A buoy is attached at the end of the A&R cable. The reel
vessel returns to the spool base to load more welded pipeline on the reel drum.
On returning, it pulls the end of the pipeline using the A&R cable, removes
the pullhead, and welds it to the pipeline on the drum. It then begins the
unreeling process again.
The main disadvantages of the
reeling method are:
- Connecting the ends of the pipeline segments
- Amount of time to re-reel the pipeline to remove a buckle
- Establishing a spool base close to the location where the pipeline is to be laid
- Concrete-coated pipelines cannot be reeled
- Only specifically designed pipe-in-pipe pipelines can be reeled
- The pipeline is plastically deformed and then straightened. Some thinning of the wall and loss of yield strength of the material in localized areas can occur (Bauschinger effect)
Shallow water depth ranges from
shore to 500 feet. Intermediate water depth is assumed to be 500 feet to 1000
feet. Deepwater is water depths greater than 1000 feet. Offshore magazine
produces a survey of most of the pipeline lay barges that work in the US every year.
This survey does not cover all the lay barges of all the countries that do
offshore work, but it does cover the bigger international ones Heerema, Saipem,
Stolt, Technip, Allseas, McDermott, Global, and Subsea 7.
Other methods that have been used
for pipeline installation are tow methods consisting of:
- Bottom tow
- Off-bottom tow
- Mid depth tow
- Surface tow
Tow methods can be used for
installing pipelines from shallow water depths to deepwater depths depending on
the design requirements.
***
Sumber:
Guo, Boyun, Shanhong Song, Jacob
Chacko, and Ali Ghalambor. USA. 2005.
https://www.youtube.com/watch?v=81R72Cywc0c
https://www.youtube.com/watch?v=Phqum0y1nhs
https://www.youtube.com/watch?v=KbEmg7WPCJg
0 komentar